Kentucky State Office Buildings

Guaranteed Energy Savings Contract

Contract Amount: $877,530

Guaranteed Savings: $78,840

This project was a Guaranteed Energy Savings Project that took place over the span of three months in Lexington, KY, London, KY, and Madisonville, KY. The project covered three buildings totaling 152,700 sq.ft. Funding for this project was 100% covered from savings with no escalation assumed for energy maintenance savings. The sale of the tax exempt lease purchase was solicited by CMTA and administered by Bank of America. This project was completed on schedule. 

  • New chiller and plant controls, new gas boiler, variable speed pumps, new DDC controls, LED lighting at Spindletop Administration Building¬†
  • Re-commissioning of HVAC controls to optimize energy efficiency at London State Office Building¬†
  • Re-commissioning of HVAC controls to optimize energy efficiency at the Madisonville State Office Building
Contact
Mr. Darren Hardin
Mr. Scotty Campbell
502-782-0348

Actual Savings $106,244 year 1 & $100,011 year 2
28% above guarantee