KCTCS: Jefferson

Guaranteed Energy Savings Contract

Contract Amount: $7,752,835

Guaranteed Savings: $638,111

This project was a performance contract for Jefferson Community and Technical College. Over 850,000 sq.ft. across four JCTC campuses were included in the project scope. The project highlights include extensive LED lighting retrofits, utility rate savings, a large-scale energy management system implementation, and HVAC replacements. HVAC upgrades include total system replacements at 4 buildings, major mechanical plant replacements at 4 buildings, and partial HVAC replacements and upgrades at 3 additional buildings. 

  • Extensive DDC Controls system upgrades/total replacements 
  • 6 boilers and 3 chillers replaced with new high-efficiency equipment 
  • Complete HVAC replacements at 3 buildings, upgrades at 7 more 
  • Interior and exterior LED fixtures, occupancy controls, and daylighting 
  • Water Efficiency Upgrades

Contact: reference available upon request

Actual Savings Averaging $784,618 per year

CMTA provided value beyond the energy upgrades and renovations by also being a strong advocate and technical asset for the college throughout our project... not only do we have the new equipment and controls, we have a resource that shares our interest in continually improving efficiency.

Pamela L. Turner

Jefferson Community and Technical College